The expansion of the Pennington County Campus is getting closer to the finish line.
Mike Kuhl, the Project Manager, says they have to strike an additional services agreement with ARC International.
That's due to equipment in the evidence building, such as fume hoods, which needs to be installed along with the building's systems, like ventilation.
Despite the minor set backs Kuhl says the evidence building should be complete in January.
"The Pennington County Campus Expansion is proceeding extremely well, we're very happy with the quality of the construction; it's currently under budget and ahead of schedule," says Kuhl.
Kuhl says once the Evidence Building is finished, construction on the 100,000 square foot Administration Building will begin.