Jackson Boulevard construction on time

Posted:

The construction on Rapid City's Jackson Boulevard now moves into its second phase.

Kevin Howland, the Engineering Supervisor for the project says workers are temporary widening the east bound lanes.

That work is scheduled to be completed by mid to late November.

Weather permitting, work is expected to pick up again in January when west bound lanes close.

That's when Howland says the real work will begin, "Next year's work is everywhere, storm sewer, water, and sanitary sewer, building fire lanes, plus bike lanes, new sidewalk, also some bridge rehabilitation work."

Howland says the second phase is around 10% complete.

The Jackson Boulevard project is scheduled to be fully complete by June of 2014.

Powered by WorldNow

518 St. Joseph St.
Rapid City, SD 57701

Telephone: 605.342.2000
Fax: 605.342.7305

Couldn't find what you were looking for?
Powered by WorldNow
All content © Copyright 2000 - WorldNow and KOTA. All Rights Reserved. For more information on this site, please read our Privacy Policy and Terms of Service.